Infrastructures / Civil Works

GPA Piti Unit No. 7‐40 MW Gas Turbine Power Plant

Guam, M.I. • 2002 • $40 M
Client: ENRON / TEMES

GPA Piti Unit No.8&9 80MW Gas Turbine Power Plant

Guam, M.I. • 2002 • $80 M
Client: ENRON / GPA

Chalan Monsignor Guerrero Road Reconstruction

Saipan, M.I. • 2001 • $5 M
Client: Department of Public Works Saipan CNMI

13.8 KV/345 GPA Pagat Substation

Guam, M.I. • 2000 • $1.3 M
Client: Guam Power Authority

Repairs and Upgrading to “F‐1” Pier

Guam, M.I. • 1999 • $3 M
Client: Port Authority of Guam

New Tamuning Elementary School

Guam, M.I. • 1998 • $12 M
Client: Department of Public Works Guam, MI

Talofofo Wastewater Collector System

Guam, M.I. • 1998 • $20 M
Client: Guam Waterworks Authority

Gun Beach / Fafai Wastewater System

Guam, M.I. • 1997 • $5 M
Client: Guam Waterworks Authority

Camp Watkins Road Reconstruction

Guam, M.I. • 1996 • $10 M
Client: Department of Public Works Guam, MI

LATEST PROJECTS

Repair and Modernize Bachelor Quarters Bldg. 580, 581, & 584

This is a “Design-Build” project intended to repair and modernize Bachelor Quarters Buildings.
Part of the base mission of Camp Covington is to provide housing support to Naval Mobile Construction Battalion personnel deployed to Guam. The work is located at Building 580, 581 and 584, Camp Covington, U.S. Naval Base Guam, as indicated in the attached vicinity map. The Contracting Officer will designate the exact location of the subject project.